Direction: Answer the questions based on the following information.
Production pattern for number of units (in cubic feet) per day.

For a truck that can carry 2,000 cubic ft, hiring cost per day is Rs. 1,000. Storing cost per cubic feet is Rs. 5 per day.
If all the units should be sent to the market, then on which days should the trucks be hired to minimize the cost?